Roofing Labor Cost Calculator

Area and productivity give labour hours; hours and rate give the wage. The number that decides whether the job was priced correctly is the burden sitting on top of it.

Quick answer: 16 squares at 2.5 hours each is 40 labour hours. At $45 an hour the wage is $1,800 — and the job costs $2,196 at the calculator's 22% burden, or $2,572 at the national average of about 43%. The difference is $376 on one job.

  • Area to hours to cost
  • Burden shown separately
  • Cost per square for comparison

Labour cost inputs and results

Wage, burden and productivity are specific to your business and your site.

What you'll need
  • Roof area (squares)
  • Hours per square
  • Hourly rate ($)
  • Burden (%)
Have these to hand before you start — the result updates as you type.
Labour cost
$2,196
40.0 hours · $137.25 per square · $1,800 before burden
Hours
40.0
Base wage
$1,800
Burden
$396
Per square
$137.25

A cost rather than a price; overhead and margin are added in the bid.

Show calculation

What this calculator works out

It converts a roof area into labour hours, labour hours into wages, and wages into the real cost of the crew once employer costs are added. The result is a labour cost and a cost per square.

Three things are deliberately outside it. Materials and plant are not labour, so they are not here. Overhead — the office, the vehicles, the owner’s salary — is a percentage of the whole job rather than of the wage, so it belongs in the bid. And margin is a pricing decision, not a cost, so the number this page returns is what the crew costs you, not what you charge for them.

That distinction is the reason the page exists. A labour cost that is quietly doing the work of a price is how jobs get quoted at a loss.

Inputs and results explained

Four inputs, five outputs. Three of the inputs are facts about your business; the fourth is a judgement about the roof.

InputWhat to enterLimits
Roof area (squares)The area being worked, in units of 100 sq ft. From the takeoff, not the house footprint0.1 to 5,000
Hours per squareHow long one square takes the crew, including set-up and clean-down. The only estimate of the four0.1 to 100
Hourly rate ($)The wage paid to the roofer, before any employer cost is added0 to $500
Burden (%)Employer cost as a percentage of the wage: payroll taxes, insurance, paid leave0 to 100
ResultWhat it meansUnit
Labour hoursSquares multiplied by hours per squarehours
Base wageHours multiplied by the hourly rate$
BurdenThe employer cost on top of the wage, in dollars$
Labour costBase wage plus burden — the true cost of the crew$
Per squareLabour cost divided by the area, for comparing jobs and quotes$

The output labelled labour cost is a cost, not a price. Overhead and margin are added later, in the bid — the roofing bid calculator does that step with this figure as its direct cost.

How to use the Roofing Labor Cost Calculator

Four numbers, entered in this order. Two of them are facts you already have; two are judgements you should be able to defend.

  1. Enter the roof area in squares. One square is 100 sq ft of roof surface, so a 1,600 sq ft footprint at a 6:12 pitch is about 18 squares, not 16. Use the takeoff figure, not the footprint.
  2. Enter hours per square. Start from your own past jobs if you have them. If you do not, use the covering table above and adjust for pitch, access and the crew's experience — a steep strip is closer to the top of the range than the middle.
  3. Enter the hourly rate as the wage. This is what the roofer is paid, not what you charge the customer. Entering a charge-out rate here double-counts overhead and margin, and it is the single most common way this calculation goes wrong.
  4. Enter the burden percentage. Add up what you actually pay on top of the wage: employer payroll taxes, workers’ compensation, liability insurance, paid leave and any benefits. If you have never calculated it, start with 22% and treat that as a floor rather than an answer.
  5. Read the labour cost, then read the cost per square. The per-square figure is the one to compare against your other jobs. If this job comes out at $160 a square and your last three similar jobs ran at $130, either the productivity figure is pessimistic or something about this roof is genuinely different.

The calculator updates as you type, so it is worth moving hours per square by half an hour and watching the total — that sensitivity is the point of the next section.

The burden rate is where most labour estimates go wrong

Everyone knows a roofer paid $45 an hour costs more than $45 an hour. The disagreement is about how much more, and the answer is usually larger than the number in the spreadsheet.

This calculator ships with 22% burden, which is a reasonable-looking figure and roughly half what the national data implies. In June 2026 the Bureau of Labor Statistics put private-industry employer costs at $46.89 per hour worked, of which $32.82 was wages and $14.07 was benefits. Benefits at 30.0% of total compensation is 42.9% of the wage. For full-time private workers the split is steeper still — $17.03 of benefits against $36.97 of wages, or 46.1%.

Put the other way: a $45 wage costs somewhere near $64 an hour once benefits are counted, and an estimate built on $54.90 is short by about $9 an hour for every hour on the roof.

Burden rateCost of the $45 hour16-square jobPer square
22% (default)$54.90$2,196$137.25
30%$58.50$2,340$146.25
42.9% (all private)$64.29$2,572$160.73
46.1% (full-time private)$65.73$2,629$164.32
50%$67.50$2,700$168.75

The default job: 16 squares at 2.5 hours each, 40 labour hours at $45. The difference between the 22% default and the national average is $376 on a single job, or $23.48 per square.

None of that makes 22% wrong for a particular business. A firm with no pension, a high-deductible health plan and a young crew can legitimately sit below the national average, and the BLS figure is an average across every private employer in the country rather than a target. What the comparison does is make the number something you have to defend rather than something you inherit.

What the 43% is actually made of

Burden is not one thing. It is a stack of costs that arrive on different schedules, which is why it is easy to underestimate: you notice the ones you write a cheque for and forget the ones that accrue quietly.

The BLS breakdown is instructive, because two of its components alone account for the calculator's entire default. For full-time private workers, paid leave costs $4.40 an hour and legally required benefits $3.76 — which against a $36.97 wage is 11.9% and 10.2% respectively. Together, 22.1%.

That is the default figure, and it covers holiday, sick pay and the statutory taxes, with nothing left for health insurance, retirement or anything else an employer chooses to offer. The remaining twenty-odd points of the national average are the voluntary benefits.

ComponentPer hour workedAs % of the wage
Paid leave$4.4011.9%
Legally required benefits$3.7610.2%
Insurance, retirement and other benefitsremainder of $17.03to 46.1%

Full-time private-industry workers, June 2026. Legally required benefits are Social Security, Medicare, federal and state unemployment insurance, and workers' compensation.

Two practical consequences. First, if you are pricing a subcontractor rather than an employee, most of this does not apply — a sub invoices you a rate that already contains their own burden, and adding a burden percentage on top double-counts it. Second, if you are pricing your own labour as an owner, the honest treatment is to charge the business what it would cost to replace you, burden included, or the job looks more profitable than it is.

A desk with a laptop showing a payroll spreadsheet, a printed summary sheet, a pen and a white hard hat.
The burden sits on a spreadsheet, not on the roof — which is why it is the line most often estimated from memory rather than from the payroll records.

Four inputs, and one of them dominates

The arithmetic is short. Area in squares times hours per square gives labour hours; hours times the hourly rate gives the wage; burden is a percentage on top. Four numbers, three multiplications, and only one of them is a guess.

Productivity is the guess. Hours per square is where a steep roof, a fragile covering, a difficult access or an inexperienced crew all land, and it is the input that varies most between two jobs of the same size. It is also the one with the widest plausible range: two hours a square on an easy re-cover and four on a strip-and-replace of the same area are both ordinary.

Hours per squareLabour hoursWageTotal at 42.9%Per square
2.032.0$1,440$2,057$128.58
2.540.0$1,800$2,572$160.73
3.048.0$2,160$3,086$192.87
4.064.0$2,880$4,115$257.17

16 squares at $45 an hour with a 42.9% burden throughout. Doubling the hours per square doubles the labour cost, exactly — there is no cushion anywhere in the arithmetic.

Indicative labour hours per square by covering
CoveringHours per squareWhat moves it
3-tab shingle1.5 – 2.5Fastest covering to lay; pitch and roof cuts dominate
Architectural shingle2.0 – 3.0Heavier bundles, more handling, more waste cutting
Exposed-fix metal1.5 – 2.5Panel length and fixing pattern; cuts are slow
Standing-seam metal3.0 – 5.0Seaming, clips and tolerance for expansion
Clay or concrete tile3.5 – 6.0Weight, breakage and the number of pieces per square
Cedar shake3.0 – 5.0Individual fixing, spacing and sorting
Natural slate6.0 – 10.0Grading, holing and a covering that punishes haste
Flat membrane1.5 – 3.0Seams and detail work rather than field area

Installation only, for a crew that knows the covering. Add 0.5 to 1.5 hours per square per layer for tear-off, and more again for steep or restricted access. These are planning figures, not a substitute for your own records.

Three things follow from that table. Productivity has to come from your own records, not from a rule of thumb, and the roofing labor hours estimator works backwards from crew hours if you track those instead. Where the roof is unusually steep or hard to reach, the productivity figure needs adjusting before it arrives here — that is what the roof cost factor and accessibility estimator is for. And a strip is a different job from an install: the roof tear-off cost calculator prices removal on its own rates, because the hours per square are not comparable.

What does not change the cost is crew size. Two people working twenty hours each is forty labour hours, the same as one person working forty. Crew size changes the calendar and the supervision, not the labour content — so it belongs in overhead, not here.

Two workers in yellow hard hats laying underlayment across a timber-framed pitched roof, with exposed rafters and a finished shingle slope alongside.
Crew size changes how long a job takes, not how many labour hours it contains.

Formula and calculation logic

Five lines of arithmetic. Only the burden percentage needs converting before it can be used.

StepFormulaWhat it produces
1hours = squares × hours per squareLabour hours
2base wage = hours × hourly rateWages paid
3burden = base wage × (burden % ÷ 100)Employer cost on top
4labour cost = base wage + burdenTrue cost of the crew
5per square = labour cost ÷ squaresCost per square

Variables. squares is the area in units of 100 sq ft. hours per square is crew hours, not man-hours. hourly rate is the wage in dollars. burden is a percentage of the wage.

Unit explanation. The only conversion is the burden percentage to a decimal — entering 22 means 22%, so it is divided by 100 before use. Everything else is already in the unit it is used in: squares to hours, hours to dollars.

Why burden is applied to the wage only. Employer costs follow the payroll, not the job. Materials and plant do not attract payroll tax, so applying burden to a total job cost overstates it. This calculator applies it to the wage line and nothing else, which is why the output is a labour cost rather than a job cost.

Why hours per square is multiplied, not added. Labour scales with area. A roof twice the size takes twice the hours at the same productivity, so the relationship is linear and there is no fixed component. If your jobs do have a fixed mobilisation cost, that belongs in overhead — not in hours per square, where it would distort small jobs.

Rounding. Hours are carried at full precision and displayed to one decimal. Money is rounded to whole dollars where the value is within half a cent of one, and to two decimals otherwise, so a cost per square is never rounded twice.

One job priced twice

The default job is 16 squares at 2.5 hours each — forty labour hours. At $45 an hour the wage is $1,800. What that job costs depends entirely on the burden rate, and the two figures below differ by nothing else.

At 22% burdenAt 42.9% burden
Labour hours40.040.0
Wage$1,800$1,800
Burden$396$772
Labour cost$2,196$2,572
Per square$137.25$160.73
True cost per hour$54.90$64.29

Same crew, same roof, same wage. The $376 difference is entirely the burden assumption — and it is a cost, not a margin, so it comes straight out of profit if it is not in the price.

Forty hours is about a week for one person, and $137 to $161 a square is the labour content before any overhead or profit. If a bid for this job is built on the lower figure and the business actually carries the higher one, the difference does not appear as a line anyone can see. It appears at the end of the year, as a profit that was smaller than the sum of the jobs suggested.

Where the labour line sits inside a full replacement, the roof replacement cost calculator carries it alongside material, tear-off and contingency so the proportions are visible.

Limitations and assumptions

The calculator produces a labour cost. It is not a price, and several things that will affect the job are not in it.

  • Non-productive time. Travel, loading, waiting for a delivery and weather days are real, but they are overhead rather than labour content — add them as a percentage at the bid stage, not here.
  • Overtime premium. If the job needs a Saturday, the rate changes. Enter the blended rate rather than the base one.
  • One productivity figure. A roof with a steep main field and a shallow porch needs a weighted hours-per-square, not an average of two guesses.
  • Per-head costs. Some burden is per person rather than per hour — a van, a phone, a set of harnesses. Those behave like overhead and a flat percentage will not capture them.
  • Supervision and management. Not in the labour hours unless you put it there.
  • Overhead and margin. Both come later, in the bid.

The two costs most often forgotten alongside labour are the ones with their own paperwork. A permit is a fixed charge per job rather than a rate, which the roof permit cost estimate covers. Access is the other: scaffolding is hired by area and time, and on a job that needs it the hire can approach the labour cost itself — the roof scaffolding cost estimate prices it.

And a labour cost that looks healthy on one job says nothing about the return on the roof itself. That is a different question, and the roof roi calculation answers it from the owner's side rather than the contractor's.

Frequently asked questions

Payroll taxes, workers' compensation, unemployment insurance, paid holiday and sick leave, health insurance, retirement contributions and any other benefit you fund. The statutory items and paid leave are the floor; everything above that is a choice your business has made, which is why two contractors paying the same wage can carry very different burden rates.

It is roughly the floor rather than a middle estimate. On national data, paid leave and legally required benefits alone come to about 22% of the wage — so the default covers holiday, sick pay and the statutory taxes with nothing left for health insurance or retirement. A business offering neither can sit there honestly. A business offering both is above it.

No — it blends every private employer in the country, from firms with pension schemes to ones with nothing beyond the statutory minimum. It is useful as a reference point to test your own figure against, not as an input. The right number is your payroll cost divided by your wage bill, which your payroll software will tell you.

Not in labour content. Two people working twenty hours each is forty labour hours, the same as one person working forty. What a bigger crew does change is the calendar, the supervision and the number of vans — and those are overhead, which is why crew size is not an input here.

Into overhead rather than into hours per square. Loading the truck, driving to site and standing down for rain are not productive labour, and burying them in productivity makes your hours-per-square figure wrong for the next job as well as this one. Recover them as a percentage at the bid stage.

No. A subcontractor invoices you a rate that already contains their own burden, insurance and margin. Adding a burden percentage on top double-counts it and makes the sub look far more expensive than they are. Enter subcontract labour as a cost, with burden at zero.

Enter a blended hourly rate rather than the base one, so the premium is inside the rate. Burden then applies to the blended figure, which is correct — payroll taxes are charged on the overtime rate too, so a premium carries its own burden.

No. This is a cost. Overhead and margin are added on top when the bid is built, and if you charge the labour cost to the customer you are working for nothing. The result panel says as much: a cost rather than a price.

For installation, roughly 1.5 to 2.5 hours per square for 3-tab shingle, 2 to 3 for architectural, 3.5 to 6 for tile and 6 to 10 for slate. Add 0.5 to 1.5 hours per square per layer for tear-off. Your own past jobs beat any published figure, because productivity tracks crew skill and access more than it tracks material.

Divide the labour hours by the crew size, then by productive hours per day — six is realistic once set-up and clean-down are counted. Forty labour hours is about 3.3 days for a two-person crew, not 5, because the crew works in parallel. The labour hours calculator converts in the other direction if you already track days.

Where these numbers come from

The burden comparison on this page comes from the Bureau of Labor Statistics, which publishes employer costs per hour worked every quarter.

  • Bureau of Labor Statistics — Employer Costs for Employee Compensation, June 2026 — the source for every national figure here. Private-industry employer costs averaged $46.89 per hour worked, of which $32.82 was wages and $14.07 was benefits — benefits at 30.0% of compensation, which is 42.9% of the wage. For full-time private workers, $36.97 of wages against $17.03 of benefits, or 46.1%. Within that, paid leave cost $4.40 an hour and legally required benefits $3.76, which against the wage is 11.9% and 10.2% — together 22.1%, the calculator's default.

Two cautions on using those figures. They are a national average across every private employer, not a benchmark for a roofing business in a particular state; workers' compensation in particular varies enormously by jurisdiction and by trade. And the BLS series measures cost per hour worked, which is the right basis for burden but not the same as cost per hour paid — the difference is the paid leave inside the figure.

No source is cited for hours per square, the hourly rate or the burden rate you enter, because the page asserts none of them. Productivity in particular has to come from your own job records: a published figure for roofing labour would be wrong for most roofs, since the same square can take twice as long depending on pitch, access and what is being removed.

How many days is that?

The labour hours calculator turns the same hours into crew-days using crew size and shift length.